Больше информации по резюме будет доступно после регистрации
ЗарегистрироватьсяБыл более двух недель назад
Мужчина, 41 год, родился 9 ноября 1984
Уральск, готов к переезду (Актау, Актобе, Атырау, Ирак, Иран, Королевство Саудовская Аравия, Кувейт, ОАЭ, Оман, Россия), готов к командировкам
Construction supervisor Piping&Mechanical.Pipeline Supervisor.Construction superintendent piping.
2 500 000 ₸ на руки
Специализации:
- Другое
Тип занятости: полная занятость, проектная работа/разовое задание
Опыт работы 21 год 2 месяца
Сентябрь 2022 — по настоящее время
3 года 9 месяцев
Novus BolashakFGP Future Growth Project - Wellhead Pressure Management Project Tengiz. 3GP projects. System completion and commissioning team
Атырау
3GP Commissioning Mechanical Piping Engineer
Commissioning, boundary, scope relevant drawings, and other
.eWalkdown System,Coreworx,System completion management tools.
e Walkdown Forecast, e Walkdown Tracker.
Schedule construction and System completion walkdowns in liaison with Contractor and 3GI Project Management Team
Facilitate pre-walkdown meetings to ensure all participants are aligned on the scope and expected outcome of the scheduled walkdown as detailed in the punch list procedure
Facilitate post-walkdown meetings to categorize identified punch list items and finalize them as per the punch list
Uploading Redlines to e-dossier, e-walkdown.
Reading of drawings: Layouts, P&ID, ISO.
Ability to work with Navisworks, understanding and using
Become familiar with the Project Execution Plan
Interface with the PLI Coordinators to ensure punch list items
MC Plus from walkdowns.
Responsible for the Reporting Walkdown status and progress for the project
Responsible for implementing the ME&I and SC procedures,
support project metrics.
Daily coordinate with TCO Client team to achieve MC and RFSU for each subsystem.
Construction Team to ensure effective understanding of the Walkdown and
Punch list Procedure.
Support the delivery of the Project and ME&I Team’s KPI’s, including
cascading safety Team.
Conduct daily meetings with the Mechanical team to update, closed Punches.
Conduct Pre-Walkdown, Walkdown identify and elimination Punches, preparing necessary documents for conduct Pre-Walkdown and Walkdown (Notice and Pack Index, Systemized drawings, Redlines, Final Punch List)
Conduct weekly Punch List Closure meeting
Август 2020 — Август 2022
2 года 1 месяц
Construction supervisor Piping &Mechanical at KPJV Limited (Fluor, Worley Parsons,KGNT,KING) TCO FGP 3GP projects.
Construction supervisor Piping&Mechanical
Duties & Responsibilities
Work packages to assist in addressing open issues, closing gaps, and driving the work package Walkdown bypasses daily rides to the next step in the process,puch list IWP closed. Pipe support fabrication and Installation. Piping Fabrication. equipment assembly and installation.
3GP ME&I Resolve work packages issues (I.e., constraints, open engineering items, etc.) with proper organizations to keep work packages moving through the process. Bill of material. Shop material.erection material. Piping symbol piping and instrumentation P&D.
Engineering knowledge and understanding to answer or help research questions.
Adhere to all safety rules and PPE requirements.
Provide daily reports weekly reports feedback to update metrics that track progress, performance, and proficiency daily reports weekly reports on the work of the manage
Prepares piping stress analysis reports while being responsible for quality, budget and schedule of preparing punch list reports fabrication yards
Verification of wall thickness / schedule of pipes.
Controlling traceability number during fabrication & erection.
Monitoring air blowing, water flushing, tightness test, inserting, in hence cleaning, degreasing, and
chemical cleaning activities.
Reinstatement activities and making punch list as per P&ID of those system accepted by the owner.
Systems may include compressors, fired heaters, high and low temperature systems.
Reviews client technical documentation and requirements, issues loads to allow for design of pipe rack
Knowledge of spring hanger and expansion joint design, piping line class specifications, procurement of piping, fittings, and pipe supports is essential.
Preparation of calculations including, hydraulics, process simulations, piping sizing, control valve and equipment sizing, pressure head calculations, and performance flow curves, as requiredSchedules SMP Walkdowns in liaison with the Project Construction, Turnover and Contractor based on Contractor's Walk Down Notice.
Organizes Final SMP Walkdowns in coordination with the Project Construction, Turnover Coordinators and Punch Coordinators based on Contractor MC Notifications and Project Construction schedules.
Supports the Project Construction for Pre-Hydro and 90% walk downs when required.
ESchedules SMP Walkdowns in liaison with the Project Construction, Turnover and Contractor based on Contractor's Walk Down Notice.
Organizes Final SMP Walkdowns in coordination with the Project Construction, Turnover Coordinators and Punch Coordinators based on Contractor MC Notifications and Project Construction schedules.
Supports the Project Construction for Pre-Hydro and 90% walk downs when required.
Ensures that scope relevant to engineering drawings and system boundaries are available along with other requirements before SMP Walkdowns.facilitates a pre-walkdown meeting to ensure all participants are aligned with the scope and expected outcome of the walkdown as detailed in the Punch List procedure.
Special cleaning pipes and air blowing.
nsures that scope relevant to engineering drawings and system boundaries are available along with other requirements before SMP Walkdowns.Facilitates a pre-walkdown meeting to ensure all participants are aligned with the scope and expected outcome of the walkdown as detailed in the Punch List procedure.
Май 2017 — Июль 2020
3 года 3 месяца
Piping mechanical supervisor at Petrofac Kazakhstan .Aksai. ZKO. KGBDN projects. Karachaganak Gas Debottlenecking Project
Строительство, недвижимость, эксплуатация, проектирование... Показать еще
Piping mechanical supervisor at Petrofac Kazakhstan .Aksai. ZKO.
Duties & ResponsibilitiesTo fulfill the assigned work tasks in a timely manner, taking into account the KPO plans. The work includes: conducting surveys at work sites, developing work projects, performing calculations, preparing work volumes, developing isometric drawings, layout drawings of pipe strapping and issuing drawings in isometry, design reports and technical specifications for materials assigned to the pipe strapping engineer;
Report on the progress of all assigned work to the senior engineer of the KPO company for pipe strapping;
To interact with specialists of other specialized areas and design departments in order to carry out modifications of fishing facilities according to the approved plan;
Provide technical support to construction and commissioning groups on issues related to pipe strapping;
Ensure the selection of cost-effective materials and design solutions, taking into account operating costs and standardization of equipment;
Ensure compliance of the assigned engineering and technical work with design assignments or technical specifications and applicable technical specifications, norms and standards.
Planning and execution of projects to ensure maximum productivity within optimum quality and in a safe
Piping Line checking as per Isometric.
Preparing as built Isometric as per site condition.
Preparing Isometric by referring General Arrangement drawing.
Piping fabrication of various sizes of pipes and material class
Routine inspection of progress of work.
Prepare Valve datasheet, material requisition for ordering piping material.
Coordinating work assignments with subordinates and superiors.
Attending construction coordination meetings.
Verification of material satisfaction / identification and properly punch marked or not in all fittings
and pipes. Plays a leadership role in the development of the safety culture on the project, making safety a
natural part of all work performed.
Oversee the daily construction activities at work site, including scheduling of workers, delivery of
equipment and materials, and progress of the project.Specal cleaning pipes and air blowing activities
High focus on ensuring that all aspects of the construction work
Июль 2013 — Май 2017
3 года 11 месяцев
Construction engineer at Karakudukmunai Company: Project : SINOPEC Kazakhstan Karakudukmunai oilfield
Construction engineer at Karakudukmunai Company: Project : SINOPEC Kazakhstan Karakudukmunai oilfield
Duties & Responsibilities: Experience and technical knowledge, technical supporting in installation, assembly and welding, bolt fixing for I-IV category pipeline, steel structure, III-IV hazardous classification tanks.Daily safety hours reports on work progress control of work with contractors quality control and term of construction work in the field acts of hidden work earth work pipe installation work flow lines between injection wells work with fiberglass pipes. pipe welding control assembly of metal structures pipe assemblies and obligations in the factory. Assures all mechanical engineering designs meet applicable codes and standards including company standards, API, ASME as well as others used in static and rotating equipment mechanical design.Responsible for hydraulic and pneumatic test of piping systems. Supervisor role and managed the execution of construction activities at the respective Field sites.Specal Cleaning services and air blowing.
supervise activities on site on a daily basis starting from daily tool box talks
Ноябрь 2011 — Май 2013
1 год 7 месяцев
Piping foreman at KCOI Kashagan Progects D island NCOC. Company: Сonsolidated
Piping foreman at KCOI Kashagan Progects D island NCOC.
Coordinates and supervises daily activities of crews.
Utilizes heavy equipment to excavate, install and backfill drainage pipe.
Sequences pipe installation to reduce inference with other project activities and the public.
Continually inspects work site, surveying for potential hazards or safety concerns.
Responsible for crew safety. Establishes safe work environment that complies with the Company safety program.
Observes assigned equipment to detect machinery malfunctions. Assures the proper operation maintenance of equipment.
Analyses job cost reports to ensure production is within budget.
Reviews and approves employee time reporting.
Март 2010 — Сентябрь 2011
1 год 7 месяцев
Piping foreman at Agip kco Arabtec via Сconsolidated Contractors Company. Company: Сonsolidated Contractors
Piping foreman at Agip kco Arabtec via Сconsolidated Contractors Company
Duration: May 2010 till April 2012
Duties & Responsibilities
Measure, cut, thread and assemble new pipe, placing the assembled pipe in hangers or other supports. • Assist pipe fitters in the layout, assembly, and installation of piping.
• Cut pipe and lift up to fitters.
• Fit or assist in fitting valves, couplings, or assemblies to tanks, pumps, or systems, using hand tools.
• Requisition tools and equipment, select type and size of pipe, and collect and transport materials and Equipment to work site.
• Mount brackets and hangers on walls and ceilings to hold pipes, and set sleeves or inserts to provide support for
• Disassemble and remove damaged or worn pipe.
• Clean shop, work area, and machines, using solvent and rags.
Pipe fitter at LLC Ersay Caspian Contractor.
Ersai Caspian Contractor Kuryk base
Project: Agip KCO .Mangistau oblast
Contractor: LLC Ersay Caspian Contractor
Duration: February 2007 till February 2010
Contract scope: OIL & Gas CONSTRUCTION SITE
Duties & Responsibilities
Execute all construction tasks as per project/supervisor requirements;
Plan all operations before commencing project related work in agreement with supervisor;
Apply logic and reasoning to identify the strengths and weaknesses of alternative solutions or approaches;
Manage work time efficiently and effectively;
Read and understand all project related data, blueprints etc.;
Ensure the highest health, safety and environmental standards are maintained at all times;
Perform routine maintenance on equipment and determine what action is needed;
Detect faulty operation of equipment or defective materials and notify supervisors.
Март 2007 — Февраль 2010
3 года
Pipe fitter at LLC Ersay Caspian Contractor. Ersai Caspian Contractor Kuryk base
Pipe fitter at LLC Ersay Caspian Contractor
Duration: February 2007 till February 2010
Contract scope: OIL & Gas CONSTRUCTION SITE
Duties & Responsibilities
Execute all construction tasks as per project/supervisor requirements;
Plan all operations before commencing project related work in agreement with supervisor;
Apply logic and reasoning to identify the strengths and weaknesses of alternative solutions or approaches;
Manage work time efficiently and effectively;
Read and understand all project related data, blueprints etc.;
Ensure the highest health, safety and environmental standards are maintained at all times;
Perform routine maintenance on equipment and determine what action is needed;
Detect faulty operation of equipment or defective materials and notify supervisors
Январь 2005 — Январь 2007
2 года 1 месяц
Civil Foreman at MUNAYGASKURILIS Projects TCO rotational village Shanyrak for 8000 people. Company: MUNAYGASKURILIS Co).
Civil Foreman at MUNAYGASKURILIS Projects TCO rotational village Shanyrak for 8000 people. Company: MUNAYGASKURILIS Co).
Contract scope: OIL & Gas CONSTRUCTION SITE
Duties & Responsibilities
Supervision and monitoring the execution of construction activities within the civil trade discipline, or across a number of trade disciplines, to ensure work is carried out according to specifications.
Receiving and reviewing assignments for short-term work programs, normally of at least 1 week's duration, from engineer or superintendent to ensure complete understanding of requirements.
Assessing manpower and material requirements, based on production norms, and prioritize and allocate tasks to ensure that resources are deployed for maximum effectiveness.
Providing technical advice and training for the solving of the more complex problems. Preparing regular reports on work progress and forecasting for analysis by engineer, superintendent or supervisor.
Coordinating with other trade disciplines and stores personnel to ensure the integration of work activities and ready availability of materials and consumables.
Навыки
Уровни владения навыками
Опыт вождения
Права категории B, C
Обо мне
I have experience in the EPС project and the Greenfield and Brownfield project.
18 years a mechanical /piping supervisor,Commissioning engineer, mechanical Superintendent
in related fields of construction of different piping systems, leak testing hydrotesting. Mechanical Piping Commissioning Technician and equipment connections, with extensive execute , supervising and coordination skills in oil and gas plants , workshop ,and yards. Ensure that design and procurement activities are coordinated to provide the necessary building materials for the construction and commissioning phase. Worked in various organization as a SMP engineer/mechanical / piping supervisor in global projects
Высшее образование
2021
Высшее образование
APEC CREW Leadership
Construction
2008
Высшее образование
Строительство, Стройтельство и сооружение газонефтепроводов и газонефтехранилищ
2005
Высшее образование
Уральский колледж газонефти и отраслевых технологий Диплом с отличием.
нефт и газ Диплом с отличием, Стройтельство и сооружение газонефтепроводов и газонефтехранилищ
Знание языков
Повышение квалификации, курсы
2010
Мастер по трубомонтажным работам
Учебный производственный комбинат
2008
Монтажник магистральных трубопроводов
Училище №12
Гражданство, время в пути до работы
Гражданство: Казахстан
Разрешение на работу: Ирак, Казахстан, Королевство Саудовская Аравия, Кувейт, ОАЭ, Оман, Россия, Узбекистан
Желательное время в пути до работы: Не имеет значения